Student: 0 A Design 2 LEGEND ES ID EF SLK Descrptn LS DUR LF B Build. 4 C Order 3 D Production 4 E
Student: 0 A Design 2 LEGEND ES ID EF SLK Descrptn LS DUR LF B Build. 4 C Order 3 D Production 4 E Marketing 5 INSTRUCTIONS: Calculate forward and backward passes and in the network. Given the time-phased work packages and network, load the Baseline Budget but do not include slack. Calculate the Totals and Cumulative Totals within the budget appropriately. H F Assembly 3 NOTE: Some totals and cumulative totals have been provided to help gauge your accuracy. G Launch 1 ID A B C 6 D Budget 20 32 20 66 E 27 E F 48 G 18 Totals 231 Cumulative Totals 1 2 3 Project Cost By Week ($000) A Design Build Order Production Marketing 4 B C D E F G Assembly & Test Launch 5 6 BASELINE BUDGET 7 1 10 8 8 5 16 3 16 18 9 27 30 103 133 2 10 8 5 16 6 16 10 20 153 3 8 10 20 0 16 11 4 8 14 6 12 5 12 13 14 15
Step by Step Solution
There are 3 Steps involved in it
Step: 1
To calculate the forward and backward passes in the network and determine the project schedule we need to perform critical path analysis using the pro...Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3