Question
Students undertake the role of Project Manager to identify at least ten (10) Activities for either of the following (below) cases. Students can assume that
Students undertake the role of "Project Manager" to identifyat least ten (10) Activitiesfor either of the following (below) cases. Students can assume that they have a fully capable team with the necessary skills to finish project work. AllActivities identified will be the project scope and should be a fairly comprehensive list of the significant activities necessary to complete the project. Draw upon your own experiences and/or research (i.e., online search, etc.) to develop your list of Activities. Each Activity must:
- Have plausible estimates (duration and cost) - anticipated expenses should include your time, purchase of materials, hiring of resources, etc.
- Be logically related/sequenced
- Consist of multiple subtasks (i.e., each Activity can be broken down further into several smaller tasks)
Case Option 1: Kitchen Remodel. Remodel either part or your entire kitchen. The project should take roughly one (1) month to complete. Assume that you will either hire contractors or pay friends/family to assist with at least some of the work.
Network Diagram: CaseKitchen Remodel
ID# | Activity Name | Predecessor ID#(s) | Duration | Budget | |
1 | Establish Budget | 1 day | $0.00 | ||
2 | Design new kitchen layout | Establish Budget | 2 days | $500.00 | |
3 | Purchase new appliances/kitchen supplies | Design new kitchen layout | 1 day | $14,500 | |
4 | Demolish current Kitchen | Purchase new appliances/kitchen supplies | 3 days | $750.00 | |
5 | Plumbing/Electrical work | Demolish current Kitchen | 2 days | $2,500.0 | |
6 | Professional inspection | Plumbing/Electrical work | 3 days | $200.00 | |
7 | Install new flooring | Professional inspection | 2 day | $5,000 | |
8 | Paint walls | Install new flooring | 3 days | $1,500 | |
9 | Install new countertops | Paint walls | 1 day | $2,000 | |
10 | Install new kitchen cabinets | Install new countertops | 3 days | $2,000 | |
11 | Install new appliances | Install new kitchen cabinets | 3 days | $1,000 | |
12 | Install new backsplash | Install new appliances | 2 days | $750.00 | |
Budget at Completion: 26 days
Figure 1: Network Diagram.
Step by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started