Stutz, Inc. designs and builds basketball gymnasiums. Each gymnasium is custom - built to individual customers specifications. Stutz uses job - order costing to keep

Stutz, Inc. designs and builds basketball gymnasiums. Each gymnasium is custom-built to individual customers specifications. Stutz uses job-order costing to keep track of its costs. In February it worked on three jobs. Data for these jobs are as follows:
Job 175
Job 178
Job 179
Balance 2/1
$13,790
$ 0
$0
Direct Materials
16,200
8,500
30,500
Direct Labor Cost
23,300
7,600
45,000
Machine Hours
400hrs.
300hrs.
2,000hrs.
Overhead is applied to jobs at the rate of $25 per machine hour. By February 28, Job 178 is the only one unfinished. The balance of Finished Goods on February 1 is $94,000(consisting of Job 177). Jobs 177 and 179 are sold during February. Stutz sells its product at cost plus 40%.
Calculate the balance in Work-in-Process on February 28.
Group of answer choices
$23,600
$16,100
$212,390
$0

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image_2

Step: 3

blur-text-image_3

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Global Financial Systems Stability And Risk

Authors: Jon Danielsson

1st Edition

0273774662, 9780273774662

More Books

Students also viewed these Accounting questions