Answered step by step
Verified Expert Solution
Link Copied!

Question

1 Approved Answer

Styles FACT SCENARIO B_(Questions 5-8): Geddy Construction (GC) has a written contract with Owner for the construction and renovation of a medical facility. The contract

image text in transcribed
Styles FACT SCENARIO B_(Questions 5-8): Geddy Construction (GC) has a written contract with Owner for the construction and renovation of a medical facility. The contract is divided into two phases. Phase I is for the construction of a new medical building. Phase II is for the renovation of an existing facility. GC is required to achieve substantial completion of Phase I within 540 calendar days. The contract does not establish a timeframe or deadline for the substantial completion of Phase II, nor does it expressly state that time is of the essence. The contract does, however, provide for liquidated damages in the amount of $1,500 per day in the event GC fails to achieve substantial completion of Phase I within 540 calendar days. Upon receiving notice to proceed from Owner, GC immediately mobilizes at the jobsite to begin construction. Although requested to do so, GC never submits a construction schedule to Owner. A drainage ditch runs across the site in the area where GC is supposed to construct the medical building. It is evident from GC's daily logs and other records that it first planned to divert all water flowing through the existing drainage ditch, fill the ditch, construct a suitable building pad, install concrete footings and the concrete slab, and erect the medical building. It begins to rain two days after GC starts work. The rain continues off and on for over 30 days making it impossible for GC to perform any work. After the site dries for another 15 days, GC requests a 45-day time extension from Owner. Owner refuses to allow the time extension, but does not expressly direct GC to accelerate its work. Question Group of answer choices There are two types of delay, excusable and inexcusable, under which a contractor is entitled to both time and money Here, GC did not cause the weather delay, so he should get a time extension as well as compensation for the shutdown. When a contractor experiences an excusable delay caused by an ice storm, rain or other weather event, a contractor is entitled to both time and compensation for the period of the shutdown. Here, GC should get a time extension as well as compensation for the shutdown. GC should receive a change order, increasing the time of performance due to the weather delays, but it should not get a price increase. The weather problems were beyond anyone's control and could not have been anticipated. GC might have been entitled to a time extension, but since he didn't submit a baseline schedule to the owner, the claim should be denied. X P O P hp

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Researching The Law Finding What You Need When You Need It

Authors: Amy E. Sloan

3rd Edition

1543813364, 978-1543813364

More Books

Students also viewed these Law questions

Question

Compare the three strategies for new product introduction

Answered: 1 week ago

Question

What are the skills of management ?

Answered: 1 week ago

Question

Pollution

Answered: 1 week ago

Question

The fear of making a fool of oneself

Answered: 1 week ago