SUBJECT : SOFTWARE ENGINEERING PROCESS Read the following set of activities carefully. The precedence of all activities is finish to start. Using either Arrow diagramming
SUBJECT : SOFTWARE ENGINEERING PROCESS
Read the following set of activities carefully. The precedence of all activities is finish to start. Using either Arrow diagramming method (ADM) or Precedence diagramming method (PDM), perform the following tasks.
- Draw activity model
- Using forward pass, calculate earliest start and earliest finish for each activity
- Using backward pass, calculate latest start and latest finish of each activity. Determine float
- Represent Critical path on the activity network
Complete the table showing all the information regarding each activity that has been acquired
Activity # | Activity Identifier | Activity Duration | Precedence |
1 | A | 4 | None |
2 | B | 7 | None |
3 | C | 9 | B |
4 | D | 5 | C |
5 | E | 6 | A, D |
6 | F | 4 | C, D, E |
7 | G | 5 | F |
8 | H | 2 | G |
9 | I | 5 | G, H |
Step by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started