Subway Restaurant: Processing times are 37, 46, and 37 seconds/sandwich. Every resource is staffed by one worker (m = 1) 1. What cycle time do
Subway Restaurant: Processing times are 37, 46, and 37 seconds/sandwich. Every resource is staffed by one worker (m = 1) 1. What cycle time do you need to achieve to meet the demand (160 sandwiches/hour)? 2. How many workers do you need at the minimum