Sucher Company uses a standard cost system in which manufacturing overhead costs are applied to units of product on the basis of machine hours. The
Sucher Company uses a standard cost system in which manufacturing overhead costs are applied to units of product on the basis of machine hours. The company's condensed flexible budget for manufacturing overhead is given below: Per Machine Hours Machine hour 20,000 25,000.00 30,000.00 Variable overhead costs 3.00 Fixed overhead costs 60,000.00 75000 90000 Total overhead costs 300,000.00 300,000.00 300,000.00 $360,000 $375,000 $390,000 The denominator level of activity is 30,000 machine hours. Overhead costs for the year are given below: Standards call for 2.5 machine hours per unit of output. Actual activity and manufacturing overhead costs for the year are given below: Units produced 12,800 units Machine hours used 31,600 machine hours Overhead cost incurred: Variable costs 96,000.00 Fixed costs 297,000.00 What are the standard hours allowed for the input? What was the variable overhead spending variance? What was the variable overhead efficiency variance? What was the fixed overhead budget variance? What was the fixed overhead volume variance?
Sucher Company uses a standard cost system in which manufacturing overhead costs are applied to units of product on the basis of machine hours. | |||||||
The company's condensed flexible budget for manufacturing overhead is given below: | |||||||
Per | Machine Hours | ||||||
Machine hour | 20,000 | 25,000.00 | 30,000.00 | ||||
Variable overhead costs | 3.00 | ||||||
Fixed overhead costs | 60,000.00 | 75000 | 90000 | ||||
Total overhead costs | 300,000.00 | 300,000.00 | 300,000.00 | ||||
$360,000 | $375,000 | $390,000 | |||||
The denominator level of activity is 30,000 machine hours. Overhead costs for the year are given below: | |||||||
Standards call for 2.5 machine hours per unit of output. | |||||||
Actual activity and manufacturing overhead costs for the year are given below: | |||||||
Units produced | 12,800 units | ||||||
Machine hours used | 31,600 machine hours | ||||||
Overhead cost incurred: | |||||||
Variable costs | 96,000.00 | ||||||
Fixed costs | 297,000.00 | ||||||
What are the standard hours allowed for the input? | |||||||
What was the variable overhead spending variance? | |||||||
What was the variable overhead efficiency variance? | |||||||
What was the fixed overhead budget variance? | |||||||
What was the fixed overhead volume variance? | |||||||
Step by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started