Summary data for Benedict Construction Company's ( BCC ) Job 1 2 2 7 , which was completed in 2 0 2 4 , are

Summary data for Benedict Construction Company's (BCC) Job 1227, which was completed in 2024, are presented below:
Bid price $ 450,000
Contract cost: 2023(180,000)
2024(195,000)
Gross profit: 75,000
Estimated cost to complete:
12/31/2023 $ 200,000
12/31/20240
Assuming BCC recognizes revenue over time according to percentage of completion for this contract, the gross profit recognized in 2024 would be (rounded to the nearest thousand):
Note: Do not round intermediate calculations.
Multiple Choice
$6,000.
$45,000.
$39,000.
$42,000.

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

More Books

Students also viewed these Accounting questions

Question

What general conclusions can be drawn from research on experience?

Answered: 1 week ago