Summary data for Benedict Construction Co.'s (BCC) Job 1227, which was completed in 2021, are presented below: Bid price $ 450,000 Contract cost: 2020 (180,000

Summary data for Benedict Construction Co.'s (BCC) Job 1227, which was completed in 2021, are presented below:

Bid price$450,000
Contract cost:2020(180,000)
2021(195,000)
Gross profit:75,000


Estimated cost to complete:

12/31/2020$200,000
12/31/20210


Assuming BCC recognizes revenue over time according to the percentage of completion for this contract, Find the gross profit recognized in 2021. (rounded to the nearest thousand):

Step by Step Solution

3.36 Rating (159 Votes )

There are 3 Steps involved in it

Step: 1

of completion in 2020 Cost incurredTotal estimated cost 100 180000... blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Intermediate Accounting

Authors: J. David Spiceland, James Sepe, Mark Nelson, Wayne Thomas

10th edition

1260481956, 1260310175, 978-1260481952

More Books

Students also viewed these Accounting questions

Question

Explain why it is not wise to accept a null hypothesis.

Answered: 1 week ago