Sunk costs, are including any cost that: A. is paid to a third-party contractor and cannot be refunded for any reason. B. will occur if
Sunk costs, are including any cost that:
A. is paid to a third-party contractor and cannot be refunded for any reason.
B. will occur if the considered project is accepted and once incurred, cannot be recouped.
C. will be incurred if the considered project is approved.
D. will change if the considered project is started.
E. None of the above