Sunland Furniture Company started construction of a combination office and warehouse building for its own use at an estimated cost of $4,993,100on January 1, 2017.

Sunland Furniture Company started construction of a combination office and warehouse building for its own use at an estimated cost of $4,993,100on January 1, 2017. Sunland expected to complete the building by December 31, 2017. Sunland has the following debt obligations outstanding during the construction period.

Construction loan-10% interest, payable semiannually, issued December 31, 2016$1,982,700Short-term loan-8% interest, payable monthly, and principal payable at maturity on May 30, 20181,586,000Long-term loan-9% interest, payable on January 1 of eachyear. Principal payable on January 1, 20211,001,500

part 1

Assume that Sunland completed the office and warehouse building on December 31, 2017, as planned at a total cost of $5,234,800, and the weighted-average amount of accumulated expenditures was $3,806,700. Compute the avoidable interest on this project.

avoidable interest ?

part 2

Compute the depreciation expense for the year ended December 31, 2018. Sunland elected to depreciate the building on a straight-line basis and determined that the asset has a useful life of30years and a salvage value of $301,400

Depreciation Expense ?

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Advanced Financial Accounting

Authors: Richard Baker, Valdean Lembke, Thomas King, Cynthia Jeffrey

8th Edition

73526916, 978-0073526911

More Books

Students also viewed these Accounting questions