Question

1 Approved Answer

Sunny Park Tailors has been asked to make three different types of wedding suits for separate customers. The table below highlights the time taken in

Sunny Park Tailors has been asked to make three different types of wedding suits for separate customers. The table below highlights the time taken in hours for cutting and sewing (process 1) and delivery (process 2) of each of the suits.

Times Taken for Different Activities (hours)
Suit Cut and Sew Deliver
1 7 2
2 4 3
3 5 6

Assume that orders for suits have been listed in the above table in the order in which they were received.

A) Using the FCFS rule for scheduling, the sequence is 1-2-3 OR 1-3-2 OR 2-3-1 OR 3-2-1 OR 3-1-2 OR 2-1-3?

B) For the schedule developed using the FCFS rule, the total length of time taken to complete the three suits (including delivery) = _________hours (enter your response as a whole number).

C) Using Johnson's rule for 2-machine scheduling, the sequence is 1-3-2 OR 3-1-2 OR 2-3-1 OR 3-2-1 OR 1-2-3 OR 2-1-3?

D) For the schedule developed using the Johnson's rule, the total length of time taken to complete the three suits (including delivery) = _________hours (enter your response as a whole number)

E) Of the two developed schedules, Johnson's OR the FCFS rule gets the schedule finished sooner.

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Successful Project Management

Authors: Jack Gido, Jim Clements

4th Edition

9780324656152, 324656130, 978-0324656138

More Books

Students also viewed these General Management questions