Sunshine Company only produced one product and has the following costs: Number of units produced each year....................... 6,400 Variable costs per unit: Direct Materials............................................... $
Sunshine Company only produced one product and has the following costs:
Number of units produced each year....................... | 6,400 |
Variable costs per unit: | |
Direct Materials............................................... | $ 90 |
Direct Labor................................................... | $ 43 |
Variable Manufacturing Overhead...................... | $ 4 |
Variable Selling & Administrative expenses.......... | $ 6 |
Fixed costs per year: | |
Fixed Manufacturing Overhead.......................... | $ 50,000 |
Fixed Selling & Administrative expenses............. | $ 150,000 |
Compute the UNIT product cost under variable costing. Show your work!
Someday Mine uses the following activity rates from its activity-based costing to assign overhead costs to products.
ACTIVITY COST POOLS | ACTIVITY RATE |
Setting up batches | $ 54.50 per batch |
Assembling products | $ 6.00 per assembly hour |
Processing customer orders | $ 34.00 per customer order |
Data concerning two products appear below:
Product A | Product B | |
Number of batches | 26 | 31 |
Number of assembly hours | 550 | 400 |
Number of customer orders | 32 | 25 |
How much overhead cost would be assigned to Product A using the company's activity-based costing system? Show your work!
Step by Step Solution
There are 3 Steps involved in it
Step: 1
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started