Super Rat Machine Works produces sprockets for the Tree Bicycle Company. At the beginning of the year, they had the following standard costs for one

Super Rat Machine Works produces sprockets for the Tree Bicycle Company.

At the beginning of the year, they had the following standard costs for one batch of sprockets:

Direct labour (4 hours @ $12.00 per hour) $ 48.00

The actual results for the year are:

Batches produced 68,000Direct labour hours 290,000Direct labour cost per hour $ 11.00

Required:

Calculate the labour variances and use your solution to answer the following questions.

NOTE: Please enter all variances as positive numbers.

The amount of the direct labour rate variance, also called the direct labour price variance, is $____________.

Indicate if the direct labour rate variance is favourable (enter the letter F) or unfavourable (enter the letters UF).

The amount of the direct labour efficiency variance, also called the direct labour usage variance, is $____________.

Indicate if the direct labour efficiency variance is favourable (enter the letter F) or unfavourable (enter the letters UF).

The total labour variance, also called the direct labour flexible budget variance, is $___________.

Indicate if the total labour variance is favourable (enter the letter F) or unfavourable (enter the letters UF).

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Advances In Accounting Volume 23

Authors: Philip M J Reckers

1st Edition

0762314257, 9780762314256

More Books

Students also viewed these Accounting questions