SuperTank was unanimously selected over HeavyTank, which had a price tag of $23M per hull with an O&M cost of $1.6M per year. The Prime

SuperTank was unanimously selected over HeavyTank, which had a price tag of $23M per hull with an O&M cost of $1.6M per year.
The Prime Contractor's bid for SuperTank indicated the Army would need to budget $30M per vehicle, with O&M costs projected to be $1.2M per year.
David believes that the $.4M in annual O&M savings is worth the added $7M investment.
Nevertheless, being the dedicated analyst you are, you offered to do a sensitivity analysis on these two "deltas" (to vary up to +/-30%).
The study period for this vehicle is 30 years, after which time the Army expects the entire fleet will be replaced by SuperTank II.
Assume neglible salvage value and a MARR of 3.0%.

image text in transcribed

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access with AI-Powered Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Students also viewed these Finance questions