Question
1 Approved Answer
SuperTank was unanimously selected over HeavyTank, which had a price tag of $23M per hull with an O&M cost of $1.6M per year. The Prime
SuperTank was unanimously selected over HeavyTank, which had a price tag of $23M per hull with an O&M cost of $1.6M per year. |
The Prime Contractor's bid for SuperTank indicated the Army would need to budget $30M per vehicle, with O&M costs projected to be $1.2M per year. |
David believes that the $.4M in annual O&M savings is worth the added $7M investment. |
Nevertheless, being the dedicated analyst you are, you offered to do a sensitivity analysis on these two "deltas" (to vary up to +/-30%). |
The study period for this vehicle is 30 years, after which time the Army expects the entire fleet will be replaced by SuperTank II. |
Assume neglible salvage value and a MARR of 3.0%. |
Step by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started