Suppose a project plan had three distinct paths through the network. The first path consisted of activities A ( 3 days ) , B (
Suppose a project plan had three distinct paths through the network. The first path consisted of activities A days B days and C days The second path consisted of activities D days E days and F days The third path consisted of activities G days H days and I days Which is the critical path?
ADG
GHI
DEF
ABC