Suppose each x i is a 0-1 variable representing whether or not project i is selected. If project 5 must be completed before project 6,
Suppose each xi is a 0-1 variable representing whether or not project i is selected. If project 5 must be completed before project 6, the constraint would be x5 x6 0.
True or False