. Suppose that a local government had the following portfolio of projects at time t. Describe the status for each project in a couple of
. Suppose that a local government had the following portfolio of projects at time t. Describe the status for each project in a couple of sentences. Project Budget at Planned Value Earned Value Actual Cost Complete (t) (t) (t) A $30M $20M $19M $19M $25M $25M $15M $16M $20M $15M $18M $17M $15M $10M $8M $9M $10M $9M 58M $8M