Answered step by step
Verified Expert Solution
Question
1 Approved Answer
Suppose that a project selection problem has the following constraint: Projects 1 and 2 must either be both selected or both rejected. If Xi is
Suppose that a project selection problem has the following constraint: "Projects 1 and 2 must either be both selected or both rejected". If Xi is a binary variable denoting whether or not the ith project is selected, then how should that constraint be stated?
options:
a) X1 - X2 0
b) X1 - X2 0
c) X1 - X2 = 0
d) X1 + X2 = 1
e) X1 + X2 1
f) X1 + X2 = 2
Step by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started