Suppose that in a binary programming model for project selections, there are a total of five projects available for selection. Write the following constraint in

Suppose that in a binary programming model for project selections, there are a total of five projects available for selection. Write the following constraint in the standard form:

"If projects 1 and 3 are selected, then project 4 cannot be selected."

Suppose that in a binary programming model for project selections, there are a total of five projects available for selection. Write the following constraint in the standard form:

"If projects 1 and 3 are selected, then project 4 cannot be selected."

X4 X1 + X3

X1 + X3 + X4 2

X1 + X3 + X4 2

X1 + X3 - X4 3

X4 X1 + X3

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Probability and Random Processes With Applications to Signal Processing and Communications

Authors: Scott Miller, Donald Childers

2nd edition

123869811, 978-0121726515, 121726517, 978-0130200716, 978-0123869814

More Books

Students also viewed these Mathematics questions

Question

What are the main risks associated with building and having a ToC?

Answered: 1 week ago