Answered step by step
Verified Expert Solution
Question
1 Approved Answer
Suppose that the following estimates are given for costs. Pessimistic Optimistic Most Likely Building Cost 3,000,000 1,500,000 2,000,000 Furnishings Cost 1,250,000 500,000 750,000 Annual operating
Suppose that the following estimates are given for costs.
Pessimistic
Optimistic
Most Likely
Building Cost
3,000,000
1,500,000
2,000,000
Furnishings Cost
1,250,000
500,000
750,000
Annual operating and
maintenance costs
60,000
40,000
50,000
Assume Beta distribution for the costs, that the building and the furnishing costs are incurred at n = 0 and
that the given annual operating and maintenance costs are incurred at n =
1 and 2. Find the mean and the
variance of the net present value at MARR = 10 %. Assume independence among all costs and across
time.
Problem 1. Suppose that the following estimates are given for costs. Pessimistic Optimistic Most Likely 3,000,000 1,250,000 1,500,000 500,000 Building Cost Furnishings Cost Annual operating and maintenance costs 2,000,000 750,000 60,000 40,000 50,000 Assume Beta distribution for the costs, that the building and the furnishing costs are incurred at n= 0 and that the given annual operating and maintenance costs are incurred at n= 1 and 2. Find the mean and the variance of the net present value at MARR = 10 %. Assume independence among all costs and across time. Problem 2. Consider the following three projects with the means and the standard deviations of their NPV's. Assuming normal distribution and an aspiration level of $ 10,000, select the best project. Project E(NPV) 20,000 10,000 8,000 S.D.(NPV) 5,000 2,000 1,500 Problem 1. Suppose that the following estimates are given for costs. Pessimistic Optimistic Most Likely 3,000,000 1,250,000 1,500,000 500,000 Building Cost Furnishings Cost Annual operating and maintenance costs 2,000,000 750,000 60,000 40,000 50,000 Assume Beta distribution for the costs, that the building and the furnishing costs are incurred at n= 0 and that the given annual operating and maintenance costs are incurred at n= 1 and 2. Find the mean and the variance of the net present value at MARR = 10 %. Assume independence among all costs and across time. Problem 2. Consider the following three projects with the means and the standard deviations of their NPV's. Assuming normal distribution and an aspiration level of $ 10,000, select the best project. Project E(NPV) 20,000 10,000 8,000 S.D.(NPV) 5,000 2,000 1,500Step by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started