Suppose that the following estimates of activity times (in weeks) were provided for the network shown below: Activity Optimistic Most Probable Pessimistic A 5 6

Suppose that the following estimates of activity times (in weeks) were provided for the network shown below:

Activity Optimistic Most Probable Pessimistic
A 5 6 7
B 3.5 4 4.5
C 6 7 8
D 5 6 9
E 6.5 8 9
F 2 3 4
G 8 9 12
H 6 7 12

What is the probability that the project will be completed. If required, round your answers to four decimal places.

  1. Within 21 weeks? fill in the blank 1
  2. Within 23 weeks? fill in the blank 2
  3. Within 25 weeks?

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Linear Algebra With Applications

Authors: Jeffrey Holt

2nd Edition

1319057691, 9781319057695

More Books

Students also viewed these Mathematics questions