Suppose that the following estimates of activity times (in weeks) were provided for the network shown below: Activity Optimistic Most Probable Pessimistic A 5 6
Suppose that the following estimates of activity times (in weeks) were provided for the network shown below:
Activity | Optimistic | Most Probable | Pessimistic |
A | 5 | 6 | 7 |
B | 3.5 | 4 | 4.5 |
C | 6 | 7 | 8 |
D | 5 | 6 | 9 |
E | 6.5 | 8 | 9 |
F | 2 | 3 | 4 |
G | 8 | 9 | 12 |
H | 6 | 7 | 12 |
What is the probability that the project will be completed. If required, round your answers to four decimal places.
- Within 21 weeks? fill in the blank 1
- Within 23 weeks? fill in the blank 2
- Within 25 weeks?
Step by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started