Answered step by step
Verified Expert Solution
Link Copied!

Question

1 Approved Answer

Suppose that the testing of a system has been outsourced to another organization called Bug Busters. This company is located in another country and has

image text in transcribed image text in transcribed

Suppose that the testing of a system has been outsourced to another organization called Bug Busters. This company is located in another country and has marketed themselves as specialists in software testing. You have signed a contract and sent them a copy of all the code, database tables, and files they need to fulfill their end of the contract. The total expected cost or expected budget at completion for this subproject is $12,000. The contract stipulates four payments must be made after completion of each of the four testing phases. The time schedule for the testing is as follows: Test Planning 1 week, Unit Testing 2 weeks, Integrated Testing 2 weeks, and Acceptance Testing 2 weeks. The first phase of testing went as planned, but due to some problems encountered, the second payment that you authorized was more than planned. The project manager in charge of testing has assured you that the few problems they encountered could not be helped and that she does not expect them to continue in the remaining phases. As a smart project manager, you have asked Bug Busters for a work breakdown structure (WBS) and an update of their progress because you are not so sure that these problems are atypical and may continue throughout the testing process. Using the following information, conduct an earned value analysis to determine whether you believe the project will remain within its original planned budget of $12,000 and on schedule. Use a spreadsheet software package to determine the Estimate Cost to Completion (ECTC) and the Estimate Time to Completion (ETTC) for both typical and atypical variances. Planned Value Actual Cost Percent Complete Earned Value Phase 1: Test Planning (1 week) Develop Unit Test Plan Develop integration test plan Develop Acceptance test plan $ $ $ Payment 1: $ 500 600 550 1,650 $ 500 $ 600 $ 550 $ 1,650 100% 100% | 100% $ $ $ $ 500) 600 550 1,650 Phase 2: Unit Testing (2 weeks) Code walkthrough with team Test software units Identify programs that do not meet specifications Modify code Re-test units Verify code meets standards $ $ $ $ $ $ $ 600 $ 700 800 $ 1,200 500 $ 500 1.2001 $ 1.300 300 $ 400 200 $ 200 3,600 $ 4,300| 100% 100% 100% 100% 100% 100% $ $ $ $ $ $ $ 600 800 500 1.2001 300 200 3,600 Payment 2: Phase 3: Integration Testing (2 weeks) Test integration of all modules Identify components that do not meet specifications Modify code Re-test integration of modules Verify Components meet standards $ $ $ $ $ Payment 3:1 $ 600 300 1,400 400 200 2,900 $ $ $ $ $ $ 600 500 1,400 400 200 3.100) 100% 75% 50% 75% 80% $ $ $ $ $ $ 600 225 700 300 160 1,985 | Phase 4: Acceptance Testing (2 weeks) Business Review with Client $ Client tests system $ Identify units and components that do not meet specifications Modify code Retest units and components $ Verify that system meets standards Payment 4: $ A A A 400 800 550 800 700 600 3,850 0% 0% 0% 0% 0% 0% EAIA Suppose that the testing of a system has been outsourced to another organization called Bug Busters. This company is located in another country and has marketed themselves as specialists in software testing. You have signed a contract and sent them a copy of all the code, database tables, and files they need to fulfill their end of the contract. The total expected cost or expected budget at completion for this subproject is $12,000. The contract stipulates four payments must be made after completion of each of the four testing phases. The time schedule for the testing is as follows: Test Planning 1 week, Unit Testing 2 weeks, Integrated Testing 2 weeks, and Acceptance Testing 2 weeks. The first phase of testing went as planned, but due to some problems encountered, the second payment that you authorized was more than planned. The project manager in charge of testing has assured you that the few problems they encountered could not be helped and that she does not expect them to continue in the remaining phases. As a smart project manager, you have asked Bug Busters for a work breakdown structure (WBS) and an update of their progress because you are not so sure that these problems are atypical and may continue throughout the testing process. Using the following information, conduct an earned value analysis to determine whether you believe the project will remain within its original planned budget of $12,000 and on schedule. Use a spreadsheet software package to determine the Estimate Cost to Completion (ECTC) and the Estimate Time to Completion (ETTC) for both typical and atypical variances. Planned Value Actual Cost Percent Complete Earned Value Phase 1: Test Planning (1 week) Develop Unit Test Plan Develop integration test plan Develop Acceptance test plan $ $ $ Payment 1: $ 500 600 550 1,650 $ 500 $ 600 $ 550 $ 1,650 100% 100% | 100% $ $ $ $ 500) 600 550 1,650 Phase 2: Unit Testing (2 weeks) Code walkthrough with team Test software units Identify programs that do not meet specifications Modify code Re-test units Verify code meets standards $ $ $ $ $ $ $ 600 $ 700 800 $ 1,200 500 $ 500 1.2001 $ 1.300 300 $ 400 200 $ 200 3,600 $ 4,300| 100% 100% 100% 100% 100% 100% $ $ $ $ $ $ $ 600 800 500 1.2001 300 200 3,600 Payment 2: Phase 3: Integration Testing (2 weeks) Test integration of all modules Identify components that do not meet specifications Modify code Re-test integration of modules Verify Components meet standards $ $ $ $ $ Payment 3:1 $ 600 300 1,400 400 200 2,900 $ $ $ $ $ $ 600 500 1,400 400 200 3.100) 100% 75% 50% 75% 80% $ $ $ $ $ $ 600 225 700 300 160 1,985 | Phase 4: Acceptance Testing (2 weeks) Business Review with Client $ Client tests system $ Identify units and components that do not meet specifications Modify code Retest units and components $ Verify that system meets standards Payment 4: $ A A A 400 800 550 800 700 600 3,850 0% 0% 0% 0% 0% 0% EAIA

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

CLEP Financial Accounting Study Guide

Authors: Passyourclass

1st Edition

1614330115, 978-1614330110

More Books

Students also viewed these Accounting questions

Question

A 300N F 30% d 2 m Answered: 1 week ago

Answered: 1 week ago

Question

Evaluate the importance of the employee handbook.

Answered: 1 week ago

Question

Discuss the steps in the progressive discipline approach.

Answered: 1 week ago