Suppose the following costs and units of work completed were recorded on an activity: Month Monthly Expenditure Number of Work Units Completed 1 2 3

Suppose the following costs and units of work completed were recorded on an activity:

Month

Monthly Expenditure

Number of Work Units Completed

1 2 3 4 5 6

$1,200 $1,250 $1,260 $1,280 $1,290 $1,280

30 32 38 42 42 42

Answer the following questions:

  1. For each month, determine the cumulative cost, the cumulative work completed, the average cumulative cost per unit of work, and the monthly cost per unit of work.
  1. For each month, prepare a forecast of the eventual cost-to-complete the activity based on the proportion of work completed.
  1. For each month, prepare a forecast of the eventual cost-to-complete the activity based on the average productivity experienced on the activity.
  1. For each month, prepare a forecast of the eventual cost-to-complete the activity based on the productivity experienced in the previous month.
  1. Which forecasting method (b, c or d) is preferable for this activity? Why?

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Internal Auditing Assurance & Consulting Services

Authors: Kurt F Reading, Paul J Sobel, Urton L Anderson, Michael J Head, Sri Ramamoorti

1st Edition

0894136100, 9780894136108

More Books

Students also viewed these Accounting questions