Suppose you have the following information: Demand rate ( D ) = 7 9 0 units per hour Lead time ( T ) = 3

Suppose you have the following information:
Demand rate (D)=790 units per hour
Lead time(T)=38 hours
Container capacity (C)=500 units
Safety factor (x)=25%
Part 2
The number of kanban production cards is enter your response here. (Enter your response rounded up to the next whole number.)

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Management Information Systems Managing The Digital Firm

Authors: Kenneth C Laudon, Jane P Laudon

14th Edition

013389830X, 9780133898309

More Books

Students also viewed these General Management questions

Question

What is cost-volume-profit analysis?

Answered: 1 week ago

Question

=+b) What were the factors and factor levels?

Answered: 1 week ago

Question

Pollution

Answered: 1 week ago

Question

The fear of making a fool of oneself

Answered: 1 week ago