Susan is a project manager working for Lucerne Publishing. She is currently reviewing the Work table in the Task Usage view in MS Project (the

  1. Susan is a project manager working for Lucerne Publishing. She is currently reviewing the Work table in the Task Usage view in MS Project (the work table is shown in the image below). She enters 180 hours of actual work on task 18,Original art review.

Which of the following options best describes how the values in the Work table will change?

Question 1 options:

The Work value for task 18 will change to 180 hrs. The task 18 Work values and Actual values for Hany Morcos and Jane Dow will change to 90 hrs.
The Work value for task 18 will change to 180 hrs and the task 18 variance value will change to 8 hrs.
The Work value for task 18 will remain at 164 hrs. The task 18 Work values for Hany Morcos and Jane Dow will remain at 82 hrs and their task 18 Actual values will change to 90 hrs.
The Work value for task 18 will remain at 164 hrs. The red resource overallocation icon will show.

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Exploring The Hospitality Industry

Authors: John R Walker

2nd Edition

013243766X, 9780132437660

More Books

Students also viewed these General Management questions

Question

1. Avoid conflicts in the relationship

Answered: 1 week ago

Question

1. What will happen in the future

Answered: 1 week ago