Question
1 Approved Answer
Susana Factory has developed the following overhead cost formulas: Cost Formula Depreciation P 1,250 Set up P 1,000 + P0.50 per machine-hour Lubrication P 125
Susana Factory has developed the following overhead cost formulas: Cost Formula
Depreciation P 1,250 Set up P 1,000 + P0.50 per machine-hour Lubrication P 125 + P0.65 per machine-hour Utilities P 1.00 per machine-hour
Based on these cost formulas, the total overhead cost expected if 200 machine hours are worked is: a.P1,550 b. P2,250 c. P 425 d. P2,805
Step by Step Solution