Sweet Sugar Company manufactures three products (white sugar, brown sugar, and powdered sugar) in a continuous production process. Senior management has asked the controller to

Sweet Sugar Company manufactures three products (white sugar, brown sugar, and powdered sugar) in a continuous production process. Senior management has asked the controller to conduct an activity-based costing study. The controller identified the amount of factory overhead required by the critical activities of the organization as follows:

1

Activity

Budgeted Activity Cost

2

Production

$500,000.00

3

Setup

144,000.00

4

Inspection

44,000.00

5

Shipping

115,000.00

6

Customer service

84,000.00

7

Total

$887,000.00

The activity bases identified for each activity are as follows:

Activity

Activity Base

Production

Machine hours

Setup

Number of setups

Inspection

Number of inspections

Shipping

Number of customer orders

Customer service

Number of customer service requests

The activity-base usage quantities and units produced for the three products were determined from corporate records and are as follows:

Machine

Number of

Number of

Number of

Customer Service

Hours

Setups

Inspections

Customer Orders

Requests

Units

White sugar

5,000

85

220

1,150

60

10,000

Brown sugar

2,500

170

330

2,600

350

5,000

Powdered sugar

2,500

195

550

2,000

190

5,000

Total

10,000

450

1,100

5,750

600

20,000

Each product requires 0.5 machine hour per unit.

Complete the Activity Table for White sugar.

1. Determine the activity rate for each activity.*

2. Use the activity rates in (1) to determine the total and per-unit activity costs associated with all three products.*

* If required, round all per-unit amounts to the nearest cent.

White sugar

Activity

Activity-

Base

Activity

Activity

Usage

X

Rate

=

Cost

Production

insp. hours

Setup

Inspection

Shipping

Customer service

Total activity cost

Units

Activity cost per unit

Complete the Activity Table for Brown sugar.

1. Determine the activity rate for each activity.*

2. Use the activity rates in (1) to determine the total and per-unit activity costs associated with all three products.*

* If required, round all per-unit amounts to the nearest cent.

Brown sugar

Activity

Activity-

Base

Activity

Activity

Usage

X

Rate

=

Cost

Production

insp. hours

Setup

Inspection

Shipping

Customer service

Total activity cost

Units

Activity cost per unit

P

Complete the Activity Table for Powdered sugar.

1. Determine the activity rate for each activity.*

2. Use the activity rates in (1) to determine the total and per-unit activity costs associated with all three products.*

* If required, round all per-unit amounts to the nearest cent.

Powdered sugar

Activity

Activity-

Base

Activity

Activity

Usage

X

Rate

=

Cost

Production

Setup

Inspection

Shipping

Customer service

Total activity cost

Units

Activity cost per unit

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image_2

Step: 3

blur-text-image_3

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

IT Audit Control And Security

Authors: Robert R. Moeller

1st Edition

0471406767, 9780471406761

More Books

Students also viewed these Accounting questions

Question

What were your most important educational experiences?

Answered: 1 week ago

Question

Which personal relationships influenced you the most?

Answered: 1 week ago