Swifty corp beganconstructing a new plant facility in 2 0 2 5 . The building is expected to be completed on october 1 , 2
Swifty corp beganconstructing a new plant facility in The building is expected to be completed on october payments to the contractor are $ on Jan $ on April $on July and $ on Sept Swifty has secured a construction loan of $ at int on jan Swifty has no other debt outstanding. What is the interest amount to capitalize? Interest to capitalize $