Swifty Corporation began constructing a new plant facility in 2025. The building is expected to be completed on October 1, 2025. 2025 payments to
Swifty Corporation began constructing a new plant facility in 2025. The building is expected to be completed on October 1, 2025. 2025 payments to the contractor are $192,000 on January 4, $336,000 on April 1, $384,000 on July 1 and $144,000 on September 1. Swifty has secured a construction loan of $600,000 at 6% interest on January 4, 2025. Swifty has no other debt outstanding. What is the interest amount to capitalize? Interest to capitalize