T F 16. With an MRP system, managers can see the planned schedule before the actual release of orders, and therefore, they take actions such
T F 16. With an MRP system, managers can see the planned schedule before the actual release of orders, and therefore, they take actions such as expedite, de-expedite, delay, or cancel orders; change order quantities; advance or delay order due dates; and make changes in the master production schedule and capacity