Answered step by step
Verified Expert Solution
Question
1 Approved Answer
tab Problem #2 Crashing - has the information for the project. Answer questions A to F by completing The the tables (make sure to
tab "Problem #2 Crashing" - has the information for the project. Answer questions "A" to "F" by completing The the tables (make sure to scroll down to find parts: D, E and F. Assume an indirect cost of $300/day. Complete the tables and write up your narrative in the text box provided. Activity A B C D Path E F G H Predecessor Normal Time B A, C A, C B D E, F Crash Crash Cost Direct Cost Indirect Cost Total Cost Duration (Normal Time) 5 4 7 2 3 8 5 6 Normal Cost $500 $400 $700 $200 $300 $800 $500 $600 Crash Time Crash Cost 3 2 6 1 - 5 4 3 $1,500 $2,000 $1,600 $500 $2,900 $1,000 $1,800 Part D: The Plan for 18 days (complete the table below - there maybe more columns/rows than needed] Crash cost/day ? ? ? ? ? ? ? ? Part C Max Crash Iteration 1 Iteration 2 Iteration 3 Iteration 4 Iteration 5 Iteration 6 Iteration 7 Note: You don't need to submit the network diagram, but it is strongly recommended the you make a network diagram that you will use as you decide how many paths you have, their length, and then use the network as you crash activities. ? ? (A) List the critical activities (B) Completion time (normal time): (C) calculate crash cost per day (D), (E), and (F) Complete the tables (scroll down to see all of them). Write your answer in the text boxes provided. Part D: To get to 18 days, explain what you crashed (in order of crashing) and the total cost of the plan. Part E: The Plan for 16 days (complete the table below - there maybe more columns/rows than needed) Path Duration (Normal Time) Crash Crash Cost Direct Cost Indirect Cost Total Cost Path Part F: The Plan for the shortest possible time for this project (complete the table below - there maybe more columns/rows than needed) Duration (Normal Time) Iteration 1 Iteration 2 Iteration 3 Iteration 4 Iteration 5 Iteration 6 Iteration 7 Crashi Crash Cost Direct Cost Indirect Cost Total Cost Iteration 1 Part E: To get to 16 days, explain what you crashed (in order of crashing) and the total cost of the plan. Iteration 2 Iteration 3 Iteration 4 Iteration 5 Iteration 6 Iteration 7 Part F: What is the shortest time to complete this project, how did you get to this timing (provide what was crashed and the order) and what is the total cost for this plan?
Step by Step Solution
★★★★★
3.29 Rating (152 Votes )
There are 3 Steps involved in it
Step: 1
Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started