tab Problem #2 Crashing - has the information for the project. Answer questions A to F by completing The the tables (make sure to

 

Normal Activity Predecessor Normal Time Crash Time Crash Cost Max Crash Cost Note: You dont need to submit the network diagr

Part E: The Plan for 16 days (complete the table below - there maybe more columns/rows than needed) Part E: To get to 16 days  

 

tab "Problem #2 Crashing" - has the information for the project. Answer questions "A" to "F" by completing The the tables (make sure to scroll down to find parts: D, E and F. Assume an indirect cost of $300/day. Complete the tables and write up your narrative in the text box provided. Activity A B C D Path E F G H Predecessor Normal Time B A, C A, C B D E, F Crash Crash Cost Direct Cost Indirect Cost Total Cost Duration (Normal Time) 5 4 7 2 3 8 5 6 Normal Cost $500 $400 $700 $200 $300 $800 $500 $600 Crash Time Crash Cost 3 2 6 1 - 5 4 3 $1,500 $2,000 $1,600 $500 $2,900 $1,000 $1,800 Part D: The Plan for 18 days (complete the table below - there maybe more columns/rows than needed] Crash cost/day ? ? ? ? ? ? ? ? Part C Max Crash Iteration 1 Iteration 2 Iteration 3 Iteration 4 Iteration 5 Iteration 6 Iteration 7 Note: You don't need to submit the network diagram, but it is strongly recommended the you make a network diagram that you will use as you decide how many paths you have, their length, and then use the network as you crash activities. ? ? (A) List the critical activities (B) Completion time (normal time): (C) calculate crash cost per day (D), (E), and (F) Complete the tables (scroll down to see all of them). Write your answer in the text boxes provided. Part D: To get to 18 days, explain what you crashed (in order of crashing) and the total cost of the plan. Part E: The Plan for 16 days (complete the table below - there maybe more columns/rows than needed) Path Duration (Normal Time) Crash Crash Cost Direct Cost Indirect Cost Total Cost Path Part F: The Plan for the shortest possible time for this project (complete the table below - there maybe more columns/rows than needed) Duration (Normal Time) Iteration 1 Iteration 2 Iteration 3 Iteration 4 Iteration 5 Iteration 6 Iteration 7 Crashi Crash Cost Direct Cost Indirect Cost Total Cost Iteration 1 Part E: To get to 16 days, explain what you crashed (in order of crashing) and the total cost of the plan. Iteration 2 Iteration 3 Iteration 4 Iteration 5 Iteration 6 Iteration 7 Part F: What is the shortest time to complete this project, how did you get to this timing (provide what was crashed and the order) and what is the total cost for this plan?

Step by Step Solution

3.29 Rating (152 Votes )

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Income Tax Fundamentals 2013

Authors: Gerald E. Whittenburg, Martha Altus Buller, Steven L Gill

31st Edition

1111972516, 978-1285586618, 1285586611, 978-1285613109, 978-1111972516

More Books

Students also viewed these Accounting questions

Question

Compare and contrast licensing and subcontracting.

Answered: 1 week ago