Question
1 Approved Answer
Table 1 . Activity times in weeks table [ [ Activity , Description, table [ [ Optimistic ] , [ Time ] ]
Table Activity times in weeks
tableActivityDescription,tableOptimisticTimetableMost LikelytimetablePessimistictimetableImmediatePredecessorASite Preparation,BFoundation Construction,ACBDRoofing Installation,CEExterior Wall Construction,CFWindow and Door Installation,EGtabletablePlumbing and ElectricalRoughInDEHHVAC System Installation,GIInsulation Installation,GJDrywall Installation,GKInterior Finishing,FHI,JLFlooring Installation,KMtableCabinetry and BuiltInFurniture InstallationKNPainting and Wallpapering,bar KOtableFixture and ApplianceInstallationKPtableLandscaping and OutdoorFeaturesEQSwimming Pool Construction,PRSecurity System Installation,KQbar StableFinal Inspection and QualityControlLMNORTHandover and Occupancy,S Questions Part A:
QB has a policy of passing all the construction plans through a project review committee of
colleagues. This committee traditionally checks that all details are covered, times are realistic, and
resources are available. To be ready to answer project committee queries, Fatima wishes you to do
the followings:
a Develop a report that presents a planned schedule and expected project completion time in
weeks. Include a Gantt chart and project network in your report using MS Project.
b Find the probability of completing this project in weeks one and half year
c In addition, find out what expected completion time will ensure nearly chance of
completing the project in weeks.
d Find the probability of finishing this project in weeks.
e Find the probability of finishing this project in weeks. please answer the question AlQasr Builders, Inc. QB is a specialized firm that constructs private home dwellings for rich
customers. QB uses a standardized project format for each assignment of house construction
projects. Only activity times and unusual circumstances change the standard network. Fatima
Khurasaani has been assigned to a rich client as project manager to construct a beautiful mansion
for him. The rich client is known as Abu Hatem for his generosity and kindness. Fatima has told
Abu Hatem that a mansion of this size would typically be completed in one year and six months
about weeks Abu Hatem wants Fatima to complete the project three months earlier, before
his son's marriage, which is scheduled to take place in about months from now in one year and
three months about weeks He has told Fatima that if the mansion is completed in weeks,
he will give the firm $ extra as a bonus besides paying the negotiated construction price
of $ million for the mansion. He has also further added that for any further reduction from
weeks, he would compensate the firm with $ per week. Fatima has compiled the network
information and activity times for this project, given in Table as follows:
Step by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started