Question
1 Approved Answer
TABLE 1 begin{tabular}{|c|r|r|l|} hline Risk ID & Cost Impact & Probability & EMV Reserve Amount hline 1 & ( $ 3,000 ) & (
TABLE 1 \begin{tabular}{|c|r|r|l|} \hline Risk ID & Cost Impact & Probability & EMV Reserve Amount \\ \hline 1 & \( \$ 3,000 \) & \( 30 \% \) & \( \$ \) \\ \hline 2 & \( (\$ 1,500) \) & \( 95 \% \) &