Question
1 Approved Answer
Table 6.4 shows cost and benefit flows of two public infrastructure projects. Use a 5 percent discount rate to compute the NPV for both projects
Table 6.4 shows cost and benefit flows of two public infrastructure projects. Use a 5 percent discount rate to compute the NPV for both projects (NPV should be a simple number).
Answers:
1) NPV for project A
2) NPV for project B
2. Recalculate the NPV for both projects with a 10 percent discount rate (NPV should be a simple number).
Answers:
1) NPV for project A
2) NPV for project B
3. Write a paragraph to discuss the economic feasibility of the two projects
Project A | Personal Cost | Operating Cost | Capital Cost | Benefit |
0 | $ 300,000 | $ - | $ 200,000 | $ - |
1 | $ 150,000 | $ 2,000 | $ 100,000 | $ - |
2 | $ 100,000 | $ 15,000 | $ 25,000 | $ 30,000 |
3 | $ - | $ 21,000 | $ - | $ 150,000 |
4 | $ - | $ 21,000 | $ - | $ 200,000 |
5 | $ - | $ 21,000 | $ - | $ 200,000 |
6 | $ - | $ 21,000 | $ - | $ 200,000 |
7 | $ - | $ 21,000 | $ - | $ 200,000 |
8 | $ - | $ 25,000 | $ - | $ 200,000 |
9 | $ - | $ 25,000 | $ - | $ 200,000 |
10 | $ - | $ 25,000 | $ - | $ 200,000 |
Project B | Personal Cost | Operating Cost | Capital Cost | Benefit |
0 | $ 500,000 | $ - | $ 125,000 | $ - |
1 | $ 100,000 | $ 12,500 | $ 25,000 | $ 187,500 |
2 | $ - | $ 25,000 | $ - | $ 187,500 |
3 | $ - | $ 25,000 | $ - | $ 187,500 |
4 | $ - | $ 25,000 | $ - | $ 187,500 |
5 | $ - | $ 25,000 | $ - | $ 187,500 |
6 | $ - | $ 25,000 | $ - | $ 187,500 |
7 | $ - | $ 25,000 | $ - | $ 187,500 |
8 | $ - | $ 25,000 | $ - | $ 187,500 |
9 | $ - | $ 25,000 | $ - | $ 187,500 |
10 | $ - | $ 25,000 | $ - | $ 187,500 |
Step by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started