Question

1 Approved Answer

Table 6.4 shows cost and benefit flows of two public infrastructure projects. Use a 5 percent discount rate to compute the NPV for both projects

Table 6.4 shows cost and benefit flows of two public infrastructure projects. Use a 5 percent discount rate to compute the NPV for both projects (NPV should be a simple number).

Answers:

1) NPV for project A

2) NPV for project B

2. Recalculate the NPV for both projects with a 10 percent discount rate (NPV should be a simple number).

Answers:

1) NPV for project A

2) NPV for project B

3. Write a paragraph to discuss the economic feasibility of the two projects

Project A Personal Cost Operating Cost Capital Cost Benefit
0 $ 300,000 $ - $ 200,000 $ -
1 $ 150,000 $ 2,000 $ 100,000 $ -
2 $ 100,000 $ 15,000 $ 25,000 $ 30,000
3 $ - $ 21,000 $ - $ 150,000
4 $ - $ 21,000 $ - $ 200,000
5 $ - $ 21,000 $ - $ 200,000
6 $ - $ 21,000 $ - $ 200,000
7 $ - $ 21,000 $ - $ 200,000
8 $ - $ 25,000 $ - $ 200,000
9 $ - $ 25,000 $ - $ 200,000
10 $ - $ 25,000 $ - $ 200,000
Project B Personal Cost Operating Cost Capital Cost Benefit
0 $ 500,000 $ - $ 125,000 $ -
1 $ 100,000 $ 12,500 $ 25,000 $ 187,500
2 $ - $ 25,000 $ - $ 187,500
3 $ - $ 25,000 $ - $ 187,500
4 $ - $ 25,000 $ - $ 187,500
5 $ - $ 25,000 $ - $ 187,500
6 $ - $ 25,000 $ - $ 187,500
7 $ - $ 25,000 $ - $ 187,500
8 $ - $ 25,000 $ - $ 187,500
9 $ - $ 25,000 $ - $ 187,500
10 $ - $ 25,000 $ - $ 187,500

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

More Books

Students also viewed these Accounting questions