table [ [ Activity , Predecessor,Duratio ] , [ A , NONE, 2 ] , [ B , A , 4 ] , [
tableActivityPredecessor,DuratioANONE,BACADAEBFCGCDHEFIGJHI,
Part A
Draw a project network diagram from the above information.
Activities and can be shortened to a minimum of weeks; which activity would you shorten to reduce the project duration by weeks?
Why?
Explain the risk associated with leveling resources, compressing or crashing projects, and imposed durations or "catchup as the project is being implemented.