Answered step by step
Verified Expert Solution
Link Copied!

Question

1 Approved Answer

table [ [ ACTIVITY , table [ [ IMMEDIATE ] , [ PREDECESSOR ( S ) ] ] , TIME ESTIMATES ( IN

\table[[ACTIVITY,\table[[IMMEDIATE],[PREDECESSOR(S)]],TIME ESTIMATES (IN WEEKS)],[OPTIMISTIC,\table[[MOST],[LIKELY]],PESSIUISTic],[A,-,4,8,10],[B,A,2,8,24],[C,A,8,12,16],[D,A,4,6,10],[E,B,1,2,3],[F,E,C,6,8,20],[G,E,C,2,3,4],[H,F,2,2,2],[1,F,6,6,6],[1,D,G,H,4,6,12],[K,1,1,2,2,3]]
a) What is the expected (estimated) time for activity C?
b) What is the variance for activity C?
c) Based on the calculation of estimated times, what is the critical path?
d) What is the estimated time of the critical path?
e) What is the activity variance along the critical path?
f) What is the probability of completion of the project before week 36?
image text in transcribed

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Quantitative Methods For Business

Authors: Donald Waters

5th Edition

273739476, 978-0273739470

More Books

Students also viewed these General Management questions