Question:
tableActivitytableNormalTime daysNormal Cost $tableCrashTime daysCrash Cost $Immediate PredecessorsSTARTASTARTBSTARTCBDA CEA CFBGDHE FFINISHG H
a Using the normal times for each activity, what is the earliest date you can complete the project?
The corresponding project duration using the normal times is
days. Enter your response as an integer.