Question

1 Approved Answer

table [ [ Activity , table [ [ Normal ] , [ Time ( days ) ] ] , Normal Cost ( $

\table[[Activity,\table[[Normal],[Time (days)]],Normal Cost ($),\table[[Crash],[Time (days)]],Crash Cost ($),Immediate Predecessor(s)],[START,0,0,0,0,-],[A,7,50,5,290,START],[B,5,40,2,280,START],[C,4,70,2,330,B],[D,7,20,4,110,A, C],[E,6,30,6,30,A, C],[F,10,80,9,190,B],[G,8,50,5,320,D],[H,7,60,6,100,E, F],[FINISH,0,0,0,0,G, H]]
a. Using the normal times for each activity, what is the earliest date you can complete the project?
The corresponding project duration using the normal times is 24 days. (Enter your response as an integer.) Fill in the table below to show the proper schedule (time for each activity after crashing) for completing the project at minimum cost. (Enter your responses as integers.)
\table[[Activity,Time (days),Activity,Time (days)],[A,,E,-],[B,,F,-],[C,,G,-],[D,-,H,]]
image text in transcribed

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Technology Business Management

Authors: Todd Tucker

1st Edition

0997612746, 978-0997612745

More Books

Students also viewed these General Management questions

Question

4.4 Summarize the components of a job description.

Answered: 1 week ago