Table below shows the activities, immediate predecessors and activity duration of a project. Draw the AON project network. How long would it take to complete

Table below shows the activities, immediate predecessors and activity duration of a project. Draw the AON project network. How long would it take to complete this project? What is the length of the critical path? Calculate the slack time and total duration of the project

Activity Immediate Predecessor(s) Time (Days)

A - 2

B A 3

C A 4

D B 6

E D 9

F C 8

G E, F 2

H G 2

I G 3

J H, I 4

K J 4

Note: The answer must be handwritten and in an organized manner

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Operations Management

Authors: William J Stevenson

12th edition

2900078024107, 78024102, 978-0078024108

More Books

Students also viewed these General Management questions