Table below shows the activities, immediate predecessors and activity duration of a project. Draw the AON project network. How long would it take to complete
Table below shows the activities, immediate predecessors and activity duration of a project. Draw the AON project network. How long would it take to complete this project? What is the length of the critical path? Calculate the slack time and total duration of the project
Activity Immediate Predecessor(s) Time (Days)
A - 2
B A 3
C A 4
D B 6
E D 9
F C 8
G E, F 2
H G 2
I G 3
J H, I 4
K J 4
Note: The answer must be handwritten and in an organized manner
Step by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started