Question

1 Approved Answer

table [ [ , Time ( weeks ) , Immediate,,Time ( weeks ) , Immediate ] , [ Activity , a , m ,

\table[[,Time (weeks),Immediate,,Time (weeks),Immediate],[Activity,a,m,b,Predecessor(s),Activity,a,m,b,Predecessor(s)],[A,6,9,12,-,G,2,3,5,C, E],[B,1,8,24,A,H,1,1,1,F F],[C,9,12,18,A,I,5,5,5,F],[D,4,7,10,A,J,6,8,12,D, G, H],[E,1,3,4,B,K,1,1,4,I, J],[F,6,8,21,C, E,,,,,]]
a) The expected (estimated) time for activity C is 12 weeks. (Round your response to two decimal places.)
b) The variance for activity C is 1.78 weeks. (Round your response to two decimal places.)
c) Based on the calculation of the estimated times, the critical path is A-C - F - H-J - K
image text in transcribed

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image_2

Step: 3

blur-text-image_3

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Management

Authors: Chuck Williams

4th Edition

978-0324316797, 0324316798

More Books

Students also viewed these General Management questions