Question
tally ltd carry out construction contracts. The projects are completed over time. The company has three contracts in progress at the year end 30 aprial
tally ltd carry out construction contracts. The projects are completed over time. The company has three contracts in progress at the year end 30 aprial 2021
Alpha Beta gamma
000 000 000
cost incurred to date 640 1080 40
cost of complete 80 180 440
contract price 832 1200 600
work certified to date 624 912 0
progress payment received 500 960 0
tilly accrues profit on its construction contracts using the percentage of completion derived from the sales earned as work certified compared to the total contract price(output menthod)
required:
calculate the effects of the above contracts upon the financial statement at year end 30 april 2021.
Please with working otherwise i would not understand subject is internation corporate reporting.
Step by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started