Question
1 Approved Answer
Tanaka Machine Shop is considering a four-year project to improve its production efficiency. Buying a new machine press for $397,000 is estimated to result
Tanaka Machine Shop is considering a four-year project to improve its production efficiency. Buying a new machine press for $397,000 is estimated to result in $145,000 in annual pretax cost savings. The press qualifies for 100 percent bonus depreciation and it will have a salvage value at the end of the project of $46,000. The press also requires an initial investment in spare parts inventory of $15,100, along with an additional $2,100 in inventory for each succeeding year of the project. The shop's tax rate is 21 percent and its discount rate is 8 percent. Calculate the project's NPV. Note: Do not round intermediate calculations and round your answer to 2 decimal places, e.g., 32.16.
Step by Step Solution
There are 3 Steps involved in it
Step: 1
To calculate the projects Net Present Value NPV we need to consider the following cash flows 1 Initi...Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started