Tanouye Corporation keeps careful track of the time required to fill orders. Data concerning a particular order appear below: Hours 26.9 Wait time 4.8 Process
Tanouye Corporation keeps careful track of the time required to fill orders. Data concerning a particular order appear below: Hours 26.9 Wait time 4.8 Process time 0.4 Inspection time 5.4 Move time 4.8 Queue time The throughput time was: Multiple Choice 42.3 hours 15.4 hours 31.7 hours 10.6 hours