Question

1 Approved Answer

TARGET COMPANY 1 : A licence holder is selling the wind power plant licence. The licence is for 80 MW and the capacity utilization factor

TARGET COMPANY 1: A licence holder is selling the wind power plant licence. The licence is for 80 MW and the capacity utilization factor is 45%. The construction period is anticipated not to be longer than 9 months. The cost breakdown is as follows:

Generators and turbines options,you can choose any brand:

USD 30.000.000 (UK made)

EUR 25.000.000 (German made)

USD 20.000.000 (Korean made)

Local expenses TL 50.000.000 (regardless the origin of the generators &Turbines, local expenses will be incurred).

A renovation will be required in the 10th year to improve the efficiency of the grid connection. The investment is ewstimated to be not less than 10 Mil USD.

The licence holder wants the licence fee upfront.

Please construct this in EXCEL for this then, screenshot the solution and upload. I will upvote.

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Essentials Of Cost Accounting For Health Care Organizations

Authors: Steven A. Finkler

1st Edition

0834205289, 978-0834205284

More Books

Students also viewed these Accounting questions

Question

What does the SDLRS predict?

Answered: 1 week ago

Question

Compare value orientations among cultures

Answered: 1 week ago

Question

Discuss the relationship between culture and the built environment

Answered: 1 week ago