Task 1 has a duration of 3 days and must start on the first day of the project. Task 2 takes 4 days, which can
Task 1 has a duration of 3 days and must start on the first day of the project. Task 2 takes 4 days, which can only be started once Task 1 is complete, and must be finished by the end of the 10th day of the project. What is the correct late start (LS) date for Task 2, and what is Task 2's float (FL)?
Select one:
a.
LS = 7th day. FL = 3 days
b.
LS = 4th day. FL = 2 days
c.
LS = 6th day. FL = 3 days
d.
LS = 7th day. FL = 10 days