Task C is directly preceded by two tasks-task A and task B. Task A has an expected task completion time of five weeks and an
Task C is directly preceded by two tasks-task A and task B. Task A has an expected task completion time of five weeks and an ES time of week 6. Task B has an expected task completion time of seven weeks and an ES time of week 7. Task C has an expected task completion time of 10 weeks. The EF for activity C is week Question 2 options: 12 24 7 14 None of the above