Answered step by step
Verified Expert Solution
Question
1 Approved Answer
Task Description Start date End date duration Predecessors Resources labor Hours Labor Rate material cost other cos total cost 8/15/2023 8/21/2023 1 week Project Manager
Task Description Start date End date duration Predecessors Resources labor Hours Labor Rate material cost other cos total cost 8/15/2023 8/21/2023 1 week Project Manager 40 55 500 1,000 3700 1 Project Launch 8/15/2023 8/19/2023 4 days 1 Construction Manager 60 55 1,000 500 4,800 2 Submit Proposal Plan 8/20/2023 1/25/2023 5 days 2 Evaluation Team 80 55 1,000 5,400 3 Assessment and selection of proposals 4 Negotiation in contract 8/26/2023 8/31/2023 6 days 3 legal team / project manager 100 55 2,000 7,500 5 Planning and Design 9/1/2023 10/12/2023 6 weeks 4 architect/ Design team 400 65 10,000 5,000 41,000 6 Environmental Examines 9/1/2023 8/15/2023 2 weeks 4 Environmental consultants 160 72 4,000 1,000 16,520 7 Geotechnical Expertise 9/16/2023 10/1/2023 2 weeks 6 Geotechnical Engineers 200 72 5,000 1,500 20,900 10/7/2023 1 week 4 Evaluation Team 65 1,500 8 Choosing Construction Manager 10/1/2023 80 6,700 10/8/2023 10/14/2023 1 week 8 Project Manager 60 58 1,000 4,480 9 Team Structure and employment 10/15/2023 10/21/2023 1 week 9 Construction Manager 40 61 500 2,940 10 Licensing Requests 10/22/2023 11/5/2023 2 weeks 100 67 2000 11 Beginning cost assessments 10 cost estimators 8,700 11/6/2023 11/19/2023 2 weeks 11 cost estimators / architects 120 67 2500 10,540 12 Cost Assessments for Substitute material 13 Final cost estmiate for GMP 11/20/2023 11/5/2023 2 weeks 12 cost estimators / architects 160 72 3100 14,620 11/6/2023 11/12/2023 1 week 13 evaluation team /architects 80 1600 7360 14 gurantee mazimum price proposal 72 72 2100 10,740 15 subcontrctor bidding process 11/13/2023 11/26/2023 2 weeks 14 Construction Manager / subcontractor 120 16 subcontract approval 11/27/2023 12/2/2023 1 week 15 construction manager / evulation team 60 72 900 5220 17 supplier selection 12/3/2023 12/9/2023 1 week 16 construction manager / supplier 40 72 10,500 2500 15,880 18 Phase 2: 19 Execution of maximum Price 12/10/2023 13/2023 3days 17 Legal and Financial Team 80 100 2,000 10,000 12/14/2023 12/14/2023 1 day 18 Project Manager, legal team 40 75 1,000 4,000 20 Notice to proceed 22 Owner-Initial Changes 1/1/2024 1/5/2024 5 days 20 project manager, Client 15 50 100 23 Change order Processing 1/6/2024 1/12/2024 6 Days 21 project manager, Legal team 60 75 1500 5,000 1/16/2024 4 days 22 proejet manager, Financial Team 40 100 23 Adjustments to Gurantee Maximum Price 1/13/2024 2,000 6,000 25 Project Administration 1/17/2024 2/1/2024 16 days 26 Construction Schedule Development 2/2/2024 2/9/2024 8 Days 23 project manager, scheduling team 100 80 1,000 9,000 2/10/2024 2/17/2024 7 Days 24 project manager and project Team 15 50 10,200 27 Progress Monitoring and Reporting 28 Cost control and Budget Tracking 2/18/2024 2/24/2024 7 Days 25 Project Manager, Financial Team 10 50 500 50 250 29 Compliance with regulations 2/25/2024 3/3/2024 8 Days 26 legal services, project mangment 30 Self-performed work 3/4/2024 3/14/2024 10 Days 27 project manager 500 31 Identification of work to be Self-Performer 3/15/2024 3/18/2024 4 Days 28 project manager 10 50 3/19/2024 3/24/2024 6 Days 29 project manager, construction Team 40 90 32 Execution of self-performaed work 33 subcontracted Work 3/25/2024 4/4/2024 11 Days 30 construction team 34 subcontracted selection 4/5/2024 4/8/2024 4 Days 31 project manager, procurment team 60 80 300 35 subcontract agreement 4/9/2024 4/12/2024 4 Days 32 leagl team, procurement team 40 75 1500 6,000 4/13/2024 4/20/2024 7 Days 10 70 36 tax-exempt material purchases 33 procurment team, finance team 700 4/21/2023 4/24/2024 4 Days 34 financial team, legal team 40 75 1,000 6,000 37 tax-exempt documentation phase 3 38 project completion 5/6/2024 5/10/2024 4 days 35 project Team and Quality inspector 8 50 200 600 39 final inspection 5/11/2024 5/16/2024 6 Days 20 50 1,000 40 Punch List resolution 36 project Team, subcontractors 5/17/2024 5/21/2024 5 days 37 project manager and client 10 50 100 600 41 handover to owner 42 documentation and reporting 500 700 43 as-build documentation 5/28/2024 6/1/2024 5 days 38 project team and documentation team 20 70 2600 44 Final cost documentation 6/2/2024 6/6/2024 5 days 39 Financial team, project team 10 70 700 6/7/2024 6/10/2024 4 days 40 project manager, repoting team 15 70 1,050 45 project report 46 Project evaluation 47 post project evualtion 6/19/2024 6/22/2024 4 days 41 project manager, evaluation team 10 70 700 48 lesson learned 6/23/2024 6/26/2024 4 days 42 Project Team, Facilitator 50 400
Step by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started