Answered step by step
Verified Expert Solution
Question
1 Approved Answer
Task Immediate a m b predecessor/s A None 3 4 5 B None 2 4 6 C A 7 8 10 D B 4
Task Immediate a m b predecessor/s A None 3 4 5 B None 2 4 6 C A 7 8 10 D B 4 7 9 E C,D 3 5 7 F E 1 2 4 G C,F 5 8 9 H F 3 6 8 3.2.1 Determine the expected time and the variance of each project activity. Convert the expected time to the nearest whole number 3.2.2 Determine the critical path and completion time of the project. (12) (4) 3.2.3 Determine the project standard deviation. (2) 3.2.4 What is the probability that the project will be completed two weeks before the project completion time? (3) [27]
Step by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started