Task Predecessor Optimistic Most Likely Pessimistic A -- 5 8 10 B A 7 10 12 C B 8 10 14 D -- 11 15

Task Predecessor Optimistic Most Likely Pessimistic A -- 5 8 10 B A 7 10 12 C B 8 10 14 D -- 11 15 20 E D 12 14 18 A project manager gathers the time information for each activity, as shown in the table above. Calculate the expected time for activities A and B, respectively. Group of answer choices 7.83 and 9.83 8.81 and 8.99 7.58 and 8.81 7.83 and 8.99 8.81 and 9.83

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image_2

Step: 3

blur-text-image_3

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Welcome To Hospitality An Introduction

Authors: Kaye Chon, Kye Sung Chon

3rd Edition

1428321489, 9781428321489

More Books

Students also viewed these General Management questions

Question

Discuss how investment advisors can help their behavioral clients.

Answered: 1 week ago